Above Ground Installation
NOTE: If not backfilled, footing forms must be anchored to the ground.
Take some time to view our step-by-step animations to see how easy Bigfoot installation is!
|
|
|
|
Step One |
Step Two |
Step Three |
Step Four |
STEPS: - Excess rings should be cut off at the top of the ring being used and removed.
- Screw required length of construction tube to the footing form with four 1" screws.
- Drill 3/8 (10 mm) holes on a 45 degree angle in the footing form as indicated by the markings on the flange area at each rib location to accept 12" (300 mm) spikes. Drive 12" (300 mm) spikes in at a 45 degree angle to prevent the footing form from rising.
- Pour concrete using footing form inverted on top of the construction tube as a funnel.
Print all or part of our Installation manual (PDF files require Adobe Acrobat Reader . Download it now!)
To have a complete set of engineered documentation and instructions mailed or faxed to you, contact us!
From anywhere in North America: TF 1 800 934 0393
From anywhere in the world: (country code 011) 902 627 1600
ALSO: View the below ground installation instructions.