Below Grade Instalation
Take some time to view our step-by-step animations to see how easy Bigfoot installation is!
STEPS:
- Dig hole.
- Base should be placed on undisturbed soil or 4" - 6" of compacted crushed stone or gravel.
- Excess rings should be cut off at the top of the ring being used and removed.
- Screw required length of construction tube to the footing form with four 1" screws.
|
|
|
|
Step Four
|
Step Five
|
Step Six |
Step Nine |
- Install in hole.
- Plumb and level. The tube must be braced if it extends 3 ft. or more above grade.
- If necessary, have inspected by building inspector before backfilling.
- Backfill. Avoid dropping or placing heavy rocks or heavy wet soil on the footing form.
- Pour concrete using footing form inverted on top of the construction tube as a funnel.
Print all or part of our Installation manual (PDF files require Adobe Acrobat Reader . Download it now !)
To have a complete set of engineered documentation and instructions mailed or faxed to you, contact us!
From anywhere in North America: TF 1 800 934 0393
From anywhere in the world: (country code 011) 902 627 1600
ALSO: View the above ground installation instructions.