Click step-by-step animations and see it's simple to install our concrete footing forms! Here's our below grade 9-step process:

.

1. Dig hole.
2. Base should be placed on undisturbed soil or 4" - 6" of compacted crushed stone or gravel.
3. Excess rings should be cut off at the top of the ring being used and removed. (300 mm) spikes in at a 45 degree angle to prevent the footing form from rising.
4. Screw required length of construction tube to the footing form with four 1" screws

Bigfoot install step 4

Step 4

Bigfoot install step 5

Step 5

5. Install in hole.
6. Plumb and level. The tube must be braced if it extends 3 ft. or more above grade.
7. If necessary, have inspected by building inspector before backfilling.
8. Backfill. Avoid dropping or placing heavy rocks or heavy wet soil on the footing form.
9. Pour concrete using footing form inverted on top of the construction tube as a funnel.